A modern building with open plan office areas. It was a challenge to control the HVAC system due to the building’s complexity. Indoor and outdoor lighting is also controlled from the BMS.
Description:
The facility manager has the option of working with different modes of operation during day, night or holiday periods. The high standards of comfort conditions have been satisfied through the BMS.
Total number of BMS points 1900.
HVAC major equipment installed:
- 230 – VAV Boxes
- 29 – AHUs
- 3 – Chillers
- 2 – Boilers
- 8 – Primary Pumps
- 9 – Secondary Pumps
BMS equipment installed:
- 5 – Global Control Modules
- 4 – Local Control Modules
- 51 – MicroZone Controllers
- 230 – Microflo VAV Controllers
- Interface Controller for Network 8000
- Satchwell Sigma Software